Erlangen Wastewater Treatment Plant - Stage 4 Treatment, VE 4070 Precipitation Station, Wastewater Filter

Link to the RFP

Procurement

  • Procurement Regulations

    VOB/A

  • Procurement Process

    Public Tender

  • Division into Lots

    No

  • Alternative bids permitted

    No

  • Multiple main bids permitted

    No

Dates and Deadlines

  • Implementation period

    October 27, 2026, through July 31, 2027

  • Bid Submission Deadline

    September 22, 2026, 10:00 a.m.

  • Binding Period

    October 26, 2026

  • Deadline for applicant questions:

    September 21, 2026, 10:00 a.m.

Submission Format

electronically in text form

CPV Codes

45252130-8 Sewage treatment plant equipment

Brief description of the service

Dismantling and disposal of 2 PE precipitation tanks, each with a volume of 23 m³, round, including associated drip pans
Delivery and installation of 2 PE flocculant tanks, each with a volume of 15 m³, round, including collection pans, a maintenance platform, and a filling line
Delivery and installation of a coagulant dosing line, approx. 125 m, consisting of a DN 32 dosing hose and a PE 100 Da 110 protective pipe
Delivery and installation of level and leak detectors for coagulant tanks