Main fire station: extension and conversion
Stand: 04.01.2024
The main fire station on Äußere Brucker Straße is to be extended.
Informationen
Planning began in March 2023 and is planned to include
- New construction for the administration building - including vehicle halls, offices, workshops and training rooms
- Extension of the western vehicle hall, including for emergency services staff rooms
Expected to be completed between 2025 and 2028 - after budget funds have been made available.
to be determined in the course of planning
No citizen participation planned
Resolution on requirements in the Main, Finance and Personnel Committee on July 17, 2019