Campus Berufliche Bildung Erlangen (CBBE): New workshop wing and refurbishment of the commercial wing
Stand: 08.04.2024
Construction work at the Campus Berufliche Bildung Erlangen (CBBE) is ensuring a future-oriented teaching location for the industrial training professions at the vocational school in Erlangen. A new workshop wing is being built here and the industrial wing is being renovated.
Informationen
The current workshop wing of the CBBE will be replaced by a new building on the industrial wing of the vocational school. The four-storey commercial wing and the connecting building will then be demolished and replaced by a new building with integrated specialist classrooms. At the same time, a canteen for all schools on the campus will be built. The final step will be to renovate the IT wing and the administration wing and complete the outdoor facilities.
Start of construction "preparatory construction measures": 2nd half of 2020
Construction phase 1 - new construction of building section F: spring 2021 to fall 2023, then demolition of building sections B + E
Construction phase 2 - new construction of building sections B + E with canteen: planned from spring 2024
Completion of construction: planned for 2027
2018-2027
Total costs with furnishings: approx. 76 million euros
Participation within the framework of the legal requirements and participation of the school family (parents' council, pupils, teachers)
Decision on the draft planning in the building committee on October 8, 2019