Albert-Schweitzer-Gymnasium: Renovation and new construction of the gymnasium
Stand: 27.02.2024
Extensive renovation and new construction work is being carried out in the gymnasium area of the Albert-Schweitzer-Gymnasium. Among other things, a double sports hall suitable for handball is being built.
Informationen
The existing double sports hall will be renovated, including the basement with school theater areas. Furthermore, an additional double sports hall suitable for handball is to be added. The associated outdoor facilities will also be redesigned as part of this project.
- October 2021: Renovation of the double sports hall completed
- September 2021 to the end of 2023: New construction of the sports hall extension
- Spring 2024: Commissioning of the new hall and completion of the adjacent outdoor facilities
- By mid-2024: Outdoor facilities and redesign of the school forecourt
2017 until mid-2024
Approximately 13 million euros
Involvement of the school family (parents' council, pupils, teachers) and sports clubs
Decision on the draft planning in the building committee on July 10, 2018