Campus Berufliche Bildung Erlangen (CBBE): New workshop wing and refurbishment of the commercial wing
Stand: 28.10.2025
Construction work at the Campus Berufliche Bildung Erlangen (CBBE) ensures a future-oriented teaching location for the industrial training professions at the vocational school in Erlangen. A new workshop wing and a canteen for all schools at the Campus Berufliche Bildung Erlangen (CBBE) are being built here. The classroom and administration wing is being renovated.
Informationen
The current workshop wing of the CBBE is being replaced by a new building on the administration and classroom wing of the vocational school. The four-storey commercial wing and the connecting building were demolished and will be replaced by a new building with integrated specialist classrooms. At the same time, a canteen with preparation kitchen for all schools on the campus is being built. The final step will be to renovate the classroom and administration wings and complete the outdoor facilities.
- Start of construction "preparatory construction measures": 2nd half of 2020 completed
- Construction phase 1 - new building section F occupied in 09/2023, building sections E + B (old) demolished
- Construction phase 2 - new construction of building sections B + E with canteen: 04/2024 started, occupation planned by 09/2027
- Construction phase 3 - Renovation of classroom and administration wing: Planned after BA 2 from the end of 2027
- Open-air facilities and completion of construction: planned for summer 2029
2018-2029
Total costs with all equipment for the vocational training branches around 94 million euros
Participation within the framework of the legal requirements and participation of the school family (parents' council, pupils, teachers)
Decision on the draft planning in the building committee on October 8, 2019