City-Suburban Railway: Roadmap to the Planning Approval Process Presented

Stand: 27.11.2026

On Thursday, the City Council was presented with the detailed schedule and action plan for the planning approval phases within the Erlangen city limits.

The planning approval process is the next major milestone for the start of construction on the Stadt-Umland-Bahn (StUB) tram project, which is intended to connect the cities of Nuremberg, Erlangen, and Herzogenaurach. In this process, the government of Middle Franconia, as the competent authority, examines the project’s impacts and weighs factors such as transportation, environmental, and resident concerns. The process culminates in the planning approval decision, which is the formal prerequisite for the start of construction.

Documents for the Section to Reutles Completed

The documentation for the first planning approval section, “Am Wegfeld–Reutles,” within the city limits of Nuremberg has been completed. It will now be submitted to the Government of Middle Franconia for preliminary review before the formal process begins.

Detailed Schedule and Action Plan for Erlangen

The Erlangen urban area is characterized by a number of far-reaching urban development projects taking place along the future StUB route in parallel with the construction of the tram line.

  • In the southern part of the city, the Faculty of Engineering at Friedrich-Alexander University (FAU) is being expanded on the Siemens Campus.
  • At the same time, the Siemens Stadtquartier Süd is being developed as a new neighborhood with up to 2,000 residential units.
  • In the center of Erlangen, a neighborhood featuring residential and commercial spaces is being developed in the former Siemens Quartier Mitte, adjacent to FAU’s new Center for the Humanities in the Himbeerpalast.
  • Planning is also underway for the large parking lot west of the train station: the new Regnitzstadt neighborhood and a modern transportation hub are to be built here.

To account for and coordinate the complex processes involved in preparing the planning approval documents, the StUB Special-Purpose Association and the City of Erlangen, together with an external project manager, have developed a detailed schedule and action plan.

Timeline for the Erlangen Urban Area

The planning approval documents for the Erlangen Central Station–Haundorf and Freyeslebenstraße–Central Station/Regnitzstadt sections are expected to be submitted in 2029 and 2030, respectively. The other planning approval sections will be addressed earlier:

  • The planning approval process for the section from Nürnberg-Reutles to Freyeslebenstraße in Erlangen is scheduled to begin in 2028,
  • as will the planning approval process for the Haundorf–Herzogenaurach section.

According to the updated schedule, the StUB is set to begin operations up to Freyeslebenstraße in 2034. Completion of the remaining sections up to Herzogenaurach is scheduled for 2035/2036.

Eine rote Straßenbahn rechts neben einem Gebäude. Three cities, one rail line: the City-Suburban Railway (Photo: Christian Horn)

Investment Cost Estimate Updated

Along with the schedule and action plan, the investment cost estimate was also updated. Among other things, the revised route along Äußere Nürnberger Straße/B 4 and the cost estimates for the bridges on the A 3 and at Kosbacher Damm were taken into account. Also factored in were additional expenses for maintaining existing infrastructure as well as the so-called “compensation for benefits” for improvements, such as

  • traffic signal systems and utility lines, or
  • through accelerated bridge renovations.

The largest portion of the cost increase stems from the adjustment to reflect the change in price levels from 2022 to 2025, taking inflation into account. Accordingly, the investment costs for the project amount to 730 million euros at 2025 price levels. This figure is based on the construction price index. The previous estimate was 635 million euros at 2022 price levels. In contrast, the city’s own contribution is rising much less significantly, from 82 to 84 million euros, because the special-purpose association had assumed a higher proportion of ineligible costs in its most recent published cost estimate. Of the city’s own contribution, 41 million euros—just under half—have already been spent. Federal and state funding covering 90 percent of eligible costs remains unchanged. This funding also covers inflation-related increases.

Accompanying Projects by the City

An additional 51 million euros has been allocated for essential accompanying measures, which the city of Erlangen must bear in addition to its own contribution. After deducting the expected funding of 19 million euros, the city must invest a total of 32 million euros for these measures. These include, among other things, the central bus station at the Arcaden and a direct bike path connection to Regnitzstadt.

Other projects related to the StUB are listed separately. They open up additional urban planning opportunities and include, for example,

  • the redesign of Langemarckplatz
  • the urban design of the forecourt of the Arcaden, and
  • the parking garages in Regnitzstadt.

The estimated costs for these projects total 64 million euros. At 51 million euros, the largest share is allocated to the parking garages in the future Regnitzstadt.

View here: Presentation from the City Council meeting on November 26, 2026

Read more

A red streetcar to the right of a building.

We're building the StUB

As a sustainable and efficient transportation alternative, the City-Suburban Railway (StUB) is intended to connect the cities of Nuremberg, Erlangen, and Herzogenaurach, as well as the communities east of Erlangen.

Urban-rural railroad
Page, StUB, Railroad, Local traffic, Mobility, PUBLIC TRANSPORT, mobile, Public, Building project, eMobility, electro, Environment, Climate, Climate awakening, Climate awakening, Sustainability

Urban-Rural Railway - StUB

The Stadt-Umland-Bahn (StUB) was planned together with you. As a sustainable and efficient transport alternative for the region, it will connect the cities of Nuremberg, Erlangen and Herzogenaurach as well as the municipalities to the east of Erlangen.

Mobility Planning Department

Anschrift

Gebbertstraße 1
91052 Erlangen

Öffnungszeiten

jetzt geschlossen
Montag: 09:00 - 12:00 Uhr
Dienstag: 09:00 - 12:00 Uhr
Mittwoch: 09:00 - 12:00 Uhr
Donnerstag: 09:00 - 12:00 Uhr
Freitag: 09:00 - 12:00 Uhr

Individual appointments can also be arranged.

Zum Anzeigen des Standortes müssen zusätzliche Skripte geladen werden